FRV first BESS project in Finland
It is FRV´s first joint Battery Energy Storage System (BESS) 60 MWh site in Simo, Finland, located at the top of the Baltic Sea, just over 100 kilometers below the Arctic Circle.
Construction of the first phase of the project started in May 2024 and is expected to be operative in Q1 2025. Located near the newly commissioned Fingrid Simojoki substation in Lapland, the site will initially house 26 Sungrow PowerTitan battery arrays based on lithium ferrophosphate (LFP) cells, delivering 60 MWh of capacity. The project covers a 0.4-hectare area and will play a vital role in stabilizing Finland’s growing renewable energy grid.
Overview
60
MW DC
Peak Power
Simo / Finland
Location
60
MWh
Capacity
1
Hectares
Surface
2025
Operation date
In construction
Project status